A subcontractor or material supplier has how many days to file a lien once a Notice of Completion has been recorded?

Prepare for the California Landscaping Contractor C-27 License Exam. Utilize flashcards, multiple-choice questions, explanations, and hints. Ace your test!

Multiple Choice

A subcontractor or material supplier has how many days to file a lien once a Notice of Completion has been recorded?

Explanation:
In California, once a Notice of Completion is recorded, a subcontractor or material supplier has 60 days to file a mechanics lien. This shorter window is set to wrap up lien rights more quickly after the project moves toward completion, while still protecting those who contributed labor or materials. To preserve those rights in the first place, a Preliminary Notice should typically be served within 20 days of first furnishing labor or materials, and the lien must be filed in the proper county recorder’s office within the applicable deadline.

In California, once a Notice of Completion is recorded, a subcontractor or material supplier has 60 days to file a mechanics lien. This shorter window is set to wrap up lien rights more quickly after the project moves toward completion, while still protecting those who contributed labor or materials. To preserve those rights in the first place, a Preliminary Notice should typically be served within 20 days of first furnishing labor or materials, and the lien must be filed in the proper county recorder’s office within the applicable deadline.